Environmental Statement December 2011
E.ON submitted a planning application for the proposed development to the Department of Energy and Climate Change (DECC) in August 2009. There has since been ongoing dialogue and provision of technical information to various stakeholders on a variety of issues.
A copy of our Environmental Statement Further Information reports is attached below and is available for examination by the public, from Wednesday 7th December 2011 at the following locations:
North Somerset Council offices
Bristol City Council offices
Bristol central library
Portishead library
Pill library
Formal representations regarding the Environmental Statement Further Information report need to be sent to DECC by Friday 20 January 2012, either in writing or by email, at:
Secretary of State for Energy and Climate Change c/o Rob Pridham,
Onshore Consents Team,
Area A 3rd Floor,
3 Whitehall Place,
London
SW1A 2AW,
Robert.Pridham@decc.gsi.gov.uk
At the end of this consultation period, DECC will determine the application, taking into account all representations received, with a view to making its final decision, anticipated in Spring 2012.
The project team would be more than happy to respond to any queries you may have about our proposals and the Environmental Statement. Please do not hesitate to contact Karin Burke on 02476 192937 or email Karin.burke@eonenergy.com if you require further information.
| Description | File Type | Download File |
|---|---|---|
|
Indicative Cable Route Indicative Cable Route |
1.63MB | |
|
Natural England response re: cable Natural England response |
57KB | |
|
Grid connection ecological assessment Atmos Assessment from Atmos |
2.4MB | |
|
Nature Conservation Designations Map overview |
4MB | |
|
Overview Map Habitat - Grid Connection Overview map |
3.7MB | |
|
Figure 2b - Phase 1 Habitat Survey inset - grid connection Map 1 of 3 |
3.51MB | |
|
Figure 2c - Phase 1 Habitat Survey inset - grid connection Map 2 of 3 |
2.67MB | |
|
Figure 2d - Phase 1 Habitat Survey inset - grid connection Map 3 of 3 |
2.5MB | |
|
Figure 3 - Protected Species Constraints - grid connection Overview of protected species |
1.5MB | |
|
E.ON Portbury Dock Site Boundary Showing Changes Figure 2 Application boundary |
1.6MB |