Kelmarsh planning documents
Supplementary Environmental Information submitted 18 June
The planning application for the proposed Kelmarsh wind farm was validated by Daventry District Council on 8 February 2010. After our application was submitted, changes in planning policy for cultural heritage/the historic environment took place with the publication of Planning Policy Statement 5: Planning for the Historic Environment. Also, English Heritage unexpectedly proceeded with the inclusion of the park and gardens at Kelmarsh Hall on the Register of Parks and Gardens of Special Historic Interest.
In light of these changes, Daventry District Council requested that we submit Supplementary Environmental Information (SEI) under Regulation 19(1). We satisfied this request on 18 June.
Planning application submitted 5 February
The planning application was submitted on 5 February 2010 to Daventry District Council. The planning documents (including the Environmental Statement and Non Technical Summary) are available for viewing at the Council offices in Daventry, at Brixworth Information Centre and from this section. Please note the size of some of the files.
Copies of the full Environmental Statement may be obtained in Adobe pdf format on CD ROM at a cost of £5. Similarly, paper copies of the Environmental Statement may be obtained at a cost of £350 + P&P each. Cheques should be made payable to E.ON Climate and Renewables UK Developments Limited and sent to: