Project timeline

The project will run between Autumn 2011 and Winter 2013 in a series of phases.

Phase 1 – Q4 2011 to Q1 2012

  • Install Home Energy Management System in 50 homes
  • Install additional monitoring equipment in trial homes
  • Start to monitor energy use and use of the basic power concept
  • Introduce heating control
  • Identify candidates for phase 2

Phase 2 – Q2 2012 to Q4 2012

  • Upgrade 5-20 participant homes to test white goods, hot water and mobility concepts
  • Maintain a control group of about 20-25 participants and investigate changing attitudes to energy
  • Identify any changes in cost, comfort, convenience and carbon benefits for participants

Phase 3 – Q4 2012 - Q1 2013

  • Examine further concepts during heating season
  • Increase complexity of existing concepts
  • Upgrade control group to new concepts, developed during Phase 2

 